Niki, As a reminder, you can always access this page by navigating to www.GoSimpleSolar.com/Stefanelli.
Please find the “Stefanelli Project Tracker and Status”  Evernote here, this page has up to date status on all items that need to be performed to complete your project. Please refer to it often. Using this link should save on communications and keep you “up to speed” on project status. However, if you ever have any questions, please feel free to call, text, or email me!
For your information for contact info, and general schedule (minus specific dates) please reference this document:

Thank you for choosing GoSimpleSolar!

GoSimpleSolar Day-By-Day Installation Process and Contact Information
Mark Becker                                                Bob Libby                                    Nicole Becker

Mark@GoSimpleSolar.com                          Bob@GoSimpleSolar.com                  Nicole@GoSimpleSolar.com

925.915.9252                                                     925.255.3345                                      925.984.0226

Project related queries                                    Billing Queries                                    PGE

All Installation related queries                      Product Pricing                                 Pre and Post Project Admin

                                      

Pre-Project & Admin Phase: Contact Mark

Within one to three business days of receipt of your signed contract and deposit: If applicable, please provide us with the name and contact information of your Home Owner’s Association. We will coordinate document requirements and submission. Start date is subject to change, based on HOA approval. Your Installation Schedule will be emailed to you. Please reply to the “Project Coordination Form” link in the email. You will receive PG&E Net Energy Metering documents for your digital signature.

 

Project Start & Construction Phase: Contact Mark

Material delivery is usually scheduled the Friday before a planned Monday start date. A GSS representative will be there to verify all materials. Bob will then provide instructions via email with how to pay our supplier directly by credit card, if you choose. Note: Remaining project costs must be paid by check.

AFTER YOUR ROOF MODIFICATIONS are complete, the schedule should look like this:

Day One: Solar Racking Installation, usually completed on day one by California Roofing. If applicable, ventilation, plumbing, and/or gas valve modifications are made this day.

Day Two: California Roofing completes roof work. Our licensed electrician, Micor Electric, begins conduit runs and inverter mounting. Attic access is usually necessary to hide conduit runs for best aesthetics.

Day Three: Micor Electric installs solar panels after attic, electrical, and panel work.

Add ons to the system (car chargers, transfer switches, Secure Power Supply, etc.) or a large solar PV system may increase this time.

Day Four: Inspection will be scheduled for the following day, once the installation is complete. You may or may not need to be there for the inspection. Aaron will contact you with details.

Day Five: Final Building Inspection, Mark or Nicole will submit the signed off building permit to PG&E.

 

For any issues you feel may need to be addressed to company management:

Mark Becker, President: Mark@GoSimpleSolar.com, 925.915.9252

Post Project:

We’ll solicit you for comprehensive verbal or written review of our services, with the intention of getting constructive feedback so that we may always be improving our processes and our reputation. You’ll also be informed of the details of our GoSimpleSolar Sunshine Rewards referral program by Nicole Becker: Nicole@GoSimpleSolar.com 925.984.0226

 